Start build or should it be NOT start build - Innellan 1st May


Start build or should it be NOT start build



This past few months have been a total roller coaster, a mixture of problems with Gwen, numerous visits to and from Dover to check on her ability to cope and the tardiness of the structural engineer. The latter continues to cause problems, although the biggest mistake was to disappear last winter to the USA. 

The engineers are so busy with work that any excuse allows them to put our work on the back burner.  We had planning permission back in August 2015 and the structural engineer should take about two to three months to prepare their calculations and submit them to the building control. 
Obviously, nothing happened until we came back in March.


Since then we have had to amend and alter the design to take into consideration various problems. Realistically most have been due to suppliers being rather backward in thinking up in Scotland. Practices and methods often adopted in the South are not norm, so they are not readily available.

This was most evident with the block and beam flooring. In the south there is a method of using reinforced insulation blocks in between the concrete beams, therefore reducing the amount of work whilst providing far greater insulation. The companies in Scotland have never used the method and therefore would not guarantee the product being used in this situation. Very frustrating, especially when many of the companies in Scotland are sister companies of those in the south who are phisically promoting the product.

Tetris system with insulation blocks




The companies in the south were happy to provide, but the shipping costs put the product out of contention.

Other suggestions were put forward as being more cost effective, but once the cost of extra reinforced concrete had been put into the mi the cost doubled.

tata steel alternative



Eventually we had to revert to block and beam, with insulation over and reinforced concrete on top, and ultimately more insulation under the beams.

Standard block and beam system


As you can appreciate the constant changing of product had an effect on the design, the way it was laid and fitted to. Plus the depth had effect on head height on the ground floor. Something that is still outstanding, and it’s the 1st of May today.

But then again, this is tied up with the tanking in the reinforced wall on the ground floor.






Perhaps l ought to start at the beginning, to lay the foundations out so to speak.

Because of the severe slope we had two choices. We either cut out terraces and built foundation walls and build them up to the first floor level. Much as was done in our present house, which proved to be very expensive. Or the method that we eventually chose to go down. Using steel pillars that supported the main first floor slab which the timber kit home bolted onto.



 initial thoughts that l ran passed the local planners.




We were exceedingly surprised to find out that the planners were happy with all our initial intentions. Steel roof, larch cladding, narrow windows, extended balcony and elongated footprint.

So we moved onto the architect, who drew up our ideas. Through a process of discussions, ideas that were bounced around and problems thrashed out. Ultimately we came up with the plans to be put into the planners.

These were all stamped and passed in August 2015














 As previously mentioned, we then moved onto getting the building warrant from the building standards department of the council. 
But we had to get all the details checked first by the structural engineer.



The original idea was to have a few steel pillars supporting UB universal beams that cantilevered out into fresh air. Giving the impression that the house floated in mid air. Too may architectural programmes watched and admired.

It soon came to life that the beam sizes would be massive. So big that they would have required craning in. Another difficulty living over the water and up the side of a mountain (hill- not quite a munro). Its virtually impossible to get them into our area, they have to come over the ferry, then there is the cost.
So we down sized and then needed more posts. Not a problem as long as they don’t break up the room. In fact one did and does, but its in the ground floor area. We can build round it.
A problem over come. Or so we thought. But the engineer then felt it was necessary to add steel in the wooden kit home. Posts tying into the base steel that thread through the centre of the timber panels. A ring of steel then capped this off to hold it all together.
Even the roof structure didn't miss out on the steel.
The cathedral roof needed a steel beam and a steel truss.



Our first quote came in at £27k A massive expense. Fortunately, we ended up with a realistic price with a steel broker from Glasgow providing the steel and a local Dunoon fabricator cutting and welding everything on site.

The Kit home manufacturers, thought it was unnecessary and overly complicated, plus vastly more expensive. They even got their own engineer to recalculate and come back and say it was unnecessary. But ultimately, it was proved that our location was very susceptible to wind and uplift. So we decided we had to bite the bullet and go with it. 

The price of steel went up, and therefore the overall cost. We still haven't received the revised cost for the kit build.


Next question was the retaining walls on the ground floor-


Lots of variations were looked at, and eventually we came up with Gabion baskets. The steel mesh cages that are filled with stones, and used as blocks, one on top of each other.
With the site being in an area of slate, we thought it would be attractive and in keeping to fill these with the same material. Furthermore the cost of the cages and the infill was fairly inexpensive, especially once you remove the labour involved with laying blocks or brick.

As time went on, it was apparent that we needed blockwork to support the visqueen tanking. So in some respects the gabions were unnecessary. Yet we need to retain the earth, so it was then decided to make a double wall that could be in filled with reinforced concrete. BUT ONCE AGAIN we realised that the cost of the concrete was far greater than the alternative of the gabions. Pluus you still needed a second skin of block to hold the visqueen in place. You also had to fit it all out on the inside with a timber cladding.

So we are still investigating the cost merits.  




















Comments